Pittsburgh Logo
File #: 2023-2081    Version: 1
Type: Resolution Status: Passed Finally
File created: 10/20/2023 In control: Committee on Public Works and Infrastructure
On agenda: 10/24/2023 Final action: 11/6/2023
Enactment date: 11/6/2023 Enactment #: 740
Effective date:    
Title: Resolution providing for an Agreement or Agreements with Power Contracting Company for costs associated with Construction for the Pittsburgh Downtown Wayfinding project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Sixty-One Thousand Two Hundred Thirty-Five Dollars ($1,761,235.00), reimbursable at 100%.
Indexes: AGREEMENTS
Attachments: 1. 2023-2081 Cover Letter-Pittsburgh Wayfinding - Power Construction Let - signed, 2. 2023-2081 Re_ ECMS Bid Winners, 3. Summary 2023-2081

title

Resolution providing for an Agreement or Agreements with Power Contracting Company for costs associated with Construction for the Pittsburgh Downtown Wayfinding project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Sixty-One Thousand Two Hundred Thirty-Five Dollars ($1,761,235.00), reimbursable at 100%.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements with Power Contracting Company for costs associated with Construction for the Pittsburgh Downtown Wayfinding project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Sixty-One Thousand Two Hundred Thirty-Five Dollars ($1,761,235.00), reimbursable at 100%.

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

TOTAL AMOUNT

SOURCE

6074980121

40114

2021

$1,000,000.00

FHWA

6074980123

40114

2023

$761,235.00

FHWA

Total:

 

 

$1,761,235.00