Title: Resolution providing for an Agreement or Agreements with Gulisek Construction LLC for costs associated with Construction for the Critical Sidewalk Gaps project; providing for the payment of the costs thereof, not to exceed One Million One Hundred Fifty-Six Thousand Four Hundred Seventy-Five Dollars and Thirty-Five Cents ($1,156,475.35), reimbursable at 100%.
Indexes: AGREEMENTS
Attachments: 1. 2023-2079 Cover Letter-Crtiical Sidewalk Gaps - Gulisek Constructon Letter - signed, 2. 2023-2079 Re_ ECMS Bid Winners, 3. Summary 2023-2079

title

Resolution providing for an Agreement or Agreements with Gulisek Construction LLC for costs associated with Construction for the Critical Sidewalk Gaps project; providing for the payment of the costs thereof, not to exceed One Million One Hundred Fifty-Six Thousand Four Hundred Seventy-Five Dollars and Thirty-Five Cents ($1,156,475.35), reimbursable at 100%.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements with Gulisek Construction LLC for costs associated with the Construction for the Critical Sidewalk Gaps project; providing for the payment of the costs thereof, not to exceed One Million One Hundred Fifty-Six Thousand Four Hundred Seventy-Five Dollars and Thirty-Five Cents ($1,156,475.35), reimbursable at 100%.

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

TOTAL AMOUNT

SOURCE

6075010222

40114

2022

$150,438.91

FHWA

6075010123

40114

2023

$1,006,036.44

FHWA

Total:

 

 

$1,156,475.35