File #: 2022-0908    Version: 1
Type: Resolution Status: Passed Finally
File created: 11/4/2022 In control: Committee on Public Works
On agenda: 11/7/2022 Final action: 11/21/2022
Enactment date: 11/21/2022 Enactment #: 657
Effective date: 11/23/2022    
Title: Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering phase of the Swindell Bridge Construction project, and providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thousand ($1,700,000.00) dollars, an increase of Nine Hundred Thousand Dollars ($900,000.00) from the previously executed agreement (54006); reimbursable at ninety five percent; and the municipal share of Commonwealth Incurred Costs not to exceed One Thousand Five Hundred ($1,500.00) dollars, a zero Dollar ($0.00) increase from the previously executed agreement (54006).
Indexes: AGREEMENTS
Attachments: 1. 2022-0908 Cover Letter-Swindell Bridge RA Letter - signed, 2. 2022-0908-114150.Swindell.PE. Exhibit A01, 3. Summary 2022-0908
title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering phase of the Swindell Bridge Construction project, and providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thousand ($1,700,000.00) dollars, an increase of Nine Hundred Thousand Dollars ($900,000.00) from the previously executed agreement (54006); reimbursable at ninety five percent; and the municipal share of Commonwealth Incurred Costs not to exceed One Thousand Five Hundred ($1,500.00) dollars, a zero Dollar ($0.00) increase from the previously executed agreement (54006).

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering phase of the Swindell Bridge Construction project, and providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thousand ($1,700,000.00) dollars, an increase of Nine Hundred Thousand Dollars ($900,000.00) from the previously executed agreement (54006), to be paid from the following account/s:


JDE JOB NO.
JDE FUND
BUDGET YEAR
AMOUNT
SOURCE
6073870120
40020
2020
$40,000.00
Bond
6073870121
40021
2021
$ 2,500.00
Bond
6073870122
40022
2022
$31,250.00
Bond
6073870123
40023
2023
$11,250.00
Bond
6073870220
40114
2020
$760,000.00
FHWA/SHWA
6073870221
40114
2021
$47,500.00
FHWA/SHWA
6073870222
40114
2022
$593,750.00
FHWA/SHWA
6073870223
40114
2023
$213,750.00
FHWA/SHWA
Total


$1,700,000.00



Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended ...