Title: Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed Three Hundred and Fifty-Two Thousand Dollars ($352,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS
Attachments: 1. 2022-0337 Cover Letter-Sign_Elizabeth Street Street Bridge RA Letter_kal, 2. Summary 2022-0337

title

Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed Three Hundred and Fifty-Two Thousand Dollars ($352,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a no cost to the City of Pittsburgh.  Future Resolutions will authorize the project specific service agreements.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed Three Hundred and Fifty-Two Thousand Dollars ($352,000.00 to be paid from the following accounts):

 

 

Phase

JDE JOB NO.

JDE FUND

BUDGET YEAR

AMOUNT

SOURCE

Preliminary Design

6031100122

40114

2022

$352,000.00

FHWA

 

 

 

TOTAL

$352,000.00

 

 

 

Section 2.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Commonwealth of Pennsylvania, Department of Transportation for the Preliminary Design phase of the Elizabeth Street Bridge Rehabilitation Project; at a no cost to the City of Pittsburgh.