Title
Resolution amending Resolution No. 344 of 2021 entitled “Resolution providing for a Letter of Amendment to the agreement with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project, providing for the payment of municipal incurred costs thereof, not to exceed Three Million Three Hundred Fifty Thousand Dollars ($3,350,000.00); Federally reimbursable to 100 percent with a municipal share of Commonwealth Incurred Costs of Zero Dollars ($0.00).” to increase the budget authority for the construction phase to Four Million Ninety Thousand Six Hundred and Forty Dollars ($4,090,640.00), an increase of Seven Hundred Forty Thousand Six Hundred and Forty Dollars from the previously executed Agreement.
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
Resolution No. 344 of 2021, entitled “Resolution providing for a Letter of Amendment to the agreement with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project, providing for the payment of municipal incurred costs thereof, not to exceed Three Million Three Hundred Fifty Thousand Dollars ($3,350,000.00); Federally reimbursable to 100 percent with a municipal share of Commonwealth Incurred Costs of Zero Dollars ($0.00).” is hereby amended as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Letter of Amendment to the agreement with the Pennsylvania Department of Transportation for municipal incurred total phase costs associated with the Construction phase of the South Side Signals project, providing for the payment of municipal incurred total costs for the construction phase thereof, not to exceed Three Million Three Hundred Fifty Thousand Dollars ($3,350,000.00) Four Million Ninety Thousand Six Hundred and Forty Dollars ($4,090,640.00); account details to be authorized and encumbered on an individual service agreement basis. Funding for other phases authorized by resolutions 17-18 and 229-20.
Phase |
JDE JOB NO. |
JDE FUND |
BUDGET YEAR |
AMOUNT |
SOURCE |
Construction |
6071180121 |
40114 |
2021 |
$4,090,640.00 |
FHWA |
|
Total |
|
|
$4,090,640.00 |
|
Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Letter of Amendment to the agreement with the Commonwealth of Pennsylvania, Department of Transportation for the municipal portion of Commonwealth Incurred Costs associated with the Construction phase of the South Side Signals project, at a cost not to exceed Costs of Zero Dollars ($0.00).