Title
Resolution providing for a Contract or Contracts, or use of existing Contracts, providing for an Agreement or Agreements, or use of existing Agreements, and providing for the design, repairs, maintenance, improvements, emergencies and/or the purchase of materials and supplies in connection with the design and construction of the South Negley Avenue Bridge; including Construction Management Services; providing for a Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania, Department of Transportation; and providing for the payment of the costs thereof not to exceed $750,000.
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Public Works, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements, or to use existing Agreements, to enter into a Contract or Contracts, or to use existing Contracts, and to purchase materials and supplies, in connection with the design and construction of the South Negley Avenue Bridge; including Construction Management Services, providing for a Reimbursement Agreement with the Commonwealth of Pennsylvania, Department of Transportation; at a cost not to exceed $750,000.00, chargeable to and payable from the following accounts:
JDE Fund 40114
JDE Project 4030093015
Budget Year 2015
Amount $600,000 FHWA
JDE Fund 40114
JDE Project 4030093015
Budget Year 2015
Amount $112,500 SH
JDE Fund 40114
JDE Project 4030093015
Budget Year 2015
Amount $37,500 BOND
TOTAL $750,000.00
Section 2. The Mayor and the Director of the Department of Public Works, on behalf of the City of Pittsburgh, are herby authorized to enter into a Reimbursement Agreement with the Commonwealth of Pennsylvania, Department of Transportation, for reimbursement of the federal governments' share of costs to the City for the South Negley Avenue Bridge.
Finally, that any Ordinance or ...