Pittsburgh Logo
File #: 2024-0078    Version: 1
Type: Resolution Status: Passed Finally
File created: 1/26/2024 In control: Committee on Public Works and Infrastructure
On agenda: 1/30/2024 Final action: 2/6/2024
Enactment date: 2/6/2024 Enactment #: 61
Effective date: 2/15/2024    
Title: Resolution amending Resolution 512 of 2023 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty Three Million Six Hundred and Ninety Thousand Dollars ($53,690,000.00) Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00), an increase of Six Million Two Hundred Thousand Dollars ($6,200,000.00) from the previously executed agreement for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Sixty-Two Thousand Two Hundred and Fifty Dollars ($62,250.00), an increase of Fifty-Six Thousand Dollars ($56,000.00) from the previous amendment Six Thousand Two Hundred Fifty Dollars ($6,250.00). Future Resolutions will authorize the projec...
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2024-0078 Cover Letter Charles Anderson RA Amend Letter - signed, 2. 2024-0078 January 2024 TTC Packet, 3. Summary 2024-0078
title
Resolution amending Resolution 512 of 2023 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty Three Million Six Hundred and Ninety Thousand Dollars ($53,690,000.00) Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00), an increase of Six Million Two Hundred Thousand Dollars ($6,200,000.00) from the previously executed agreement for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Sixty-Two Thousand Two Hundred and Fifty Dollars ($62,250.00), an increase of Fifty-Six Thousand Dollars ($56,000.00) from the previous amendment Six Thousand Two Hundred Fifty Dollars ($6,250.00). Future Resolutions will authorize the project specific service agreements.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Fifty Three Million Six Hundred and Ninety Thousand Dollars ($53,690,000.00) Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00), an increase of Fifty Million Dollars ($50,000,000.00) Six Million Two Hundred Thousand Dollars ($6,200,000.00) for costs associated with the Construction phase of the project from the previously executed agreement, to be paid from the following account/s:


Phase
Job Number
Fund
Year
Previous Amount
Current Amount
Total Amount
Source
Preliminary Engineering
443013...

Click here for full text