Title: Resolution supplementing Resolution No. 8 of 2004 and authorizing the Mayor to execute on behalf of the City a First Amendment to the Consent Order and Agreement entered into by the City and the Pittsburgh Water and Sewer Authority with the Allegheny County Health Department and the Commonwealth of Pennsylvania Department of Environmental Protection dated January 29, 2004.
Indexes: AGREEMENTS
Attachments: 1. 2007-1634.doc
Presenter
Presented by Mr. Deasy and Mr. Bodack

Title
Resolution supplementing Resolution No. 8 of 2004 and authorizing the Mayor to execute on behalf of the City a First Amendment to the Consent Order and Agreement entered into by the City and the Pittsburgh Water and Sewer Authority with the Allegheny County Health Department and the Commonwealth of Pennsylvania Department of Environmental Protection dated January 29, 2004.

Body
WHEREAS, pursuant to Resolution No. 8 of 2004, effective January 28, 2004, the City and the Pittsburgh Water and Sewer Authority ("PWSA") entered into a Consent Order and Agreement with the Allegheny County Health Department ("ACHD") and the Commonwealth of Pennsylvania Department of Environmental Protection ("DEP") dated January 29, 2004, with Final Execution on April 21, 2004; and

WHEREAS, the aforesaid Consent Order and Agreement ("COA") obligated the City and PWSA to perform certain tasks in order to be in compliance with the Pennsylvania Clean Streams Law, Act of June 22, 1937, P.L. 1987, No. 394, as amended, 53 P.S. §§ 691.1-691.1001, and the federal Clean Water Act, Act of October 18, 1972, P.L. 92-500, 86 Stat. 880, as amended, 33 U.S.C. §§ 1251 et seq.; and

WHEREAS, the duties imposed on the City and PWSA by the COA include conducting a quality analysis and quality control analysis ("QA/QC Analysis") of flow data to be provided by the Allegheny County Sanitary Authority ("ALCOSAN"), said flow monitoring to commence by June 1, 2007; and

WHEREAS, the various obligations imposed on the City and PWSA under the COA were to be commenced or completed by dates certain, with a final termination date of June 30, 2012; and

WHEREAS, on May 31, 2007, ALCOSAN entered into a Consent Decree with United States of America, by the authority of the Attorney General of the United States, acting at the request and on behalf of the Administrator of the United States Environmental Protection Agency ("EPA"), the DEP and ...