Pittsburgh Logo
File #: 2024-0806    Version: 1
Type: Resolution Status: Reported from Standing Committee
File created: 8/23/2024 In control: Committee on Finance and Law
On agenda: 8/27/2024 Final action:
Enactment date: Enactment #:
Effective date:    
Title: Resolution further amending Resolution No. 886 of 2021, effective December 27, 2021, entitled "Resolution adopting and approving the 2022 Capital Budget and the 2022 Community Development Block Grant Program, and the 2022 through 2027 Capital Improvement Program" by reducing CBD SIGNAL UPGRADES (TIP) by Two Hundred Fifty Thousand Dollars ($250,000) and increasing COMPLETE STREETS by Two Hundred Fifty Thousand Dollars ($250,000)
Indexes: CAPITAL BUDGET (AMENDING), CDBG PROGRAM
Attachments: 1. 2024-0806 Cover Letter-2022 Complete Streets_Letter 08-19-24_JP_Signed, 2. Summary 2024-0806

title

Resolution further amending Resolution No. 886 of 2021, effective December 27, 2021, entitled “Resolution adopting and approving the 2022 Capital Budget and the 2022 Community Development Block Grant Program, and the 2022 through 2027 Capital Improvement Program” by reducing CBD SIGNAL UPGRADES (TIP) by Two Hundred Fifty Thousand Dollars ($250,000) and increasing COMPLETE STREETS by Two Hundred Fifty Thousand Dollars ($250,000)

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.       Resolution No. 886 of 2021, effective December 27, 2021, as amended, which presently reads as per Current Budget Amount, is hereby further amended to read as per Revised Budget Amount.

 

 

Fund

Job

Project

Deliverable

Dept.

Current Budget Amount

Change

Revised Budget Amount

40022

6072220122

CBD SIGNAL UPGRADES (TIP)

CBD SIGNAL UPGRADE PHASE IV - CONSTRUCTION

DOMI

$620,000

($250,000)

$370,000

40022

6074012622

COMPLETE STREETS

NORTH AVE - STREETSCAPE IMPROVEMENTS

DOMI

$0.00

$250,000

$250,000