Title: Resolution further amending and supplementing Resolution No. 855 of 2011, entitled "adopting and approving the 2012 capital budget" so as to rename District 8 DPW Projects to District 8 Intersection Improvements.
Sponsors: Erika Strassburger
Indexes: CAPITAL BUDGET (AMENDING)

title

Resolution further amending and supplementing Resolution No. 855 of 2011, entitled “adopting and approving the 2012 capital budget” so as to rename District 8 DPW Projects to District 8 Intersection Improvements.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     Amending Resolution No. 855 of 2011, as amended, so as to rename “District 8 DPW Projects” to “District 8 Intersection Improvements” as follows, in order to allow the Departments of Mobility & Infrastructure and City Planning access the District 8 Neighborhood Needs account.

 

Project Title                                                                                               

 Current Budget

 Changes   (+)(-) 

 Revised Budget

DPW-Bloomfield Deck Hockey

$74,924.55

 

$74,924.55

District 8 [DPW Projects] Intersection Improvements

$27,131.40

 

$27,131.40

Pgh Parks Conservancy-Schenley

$5,000.00

 

$5,000.00

DPW-Bike Corral

$5,868.60

 

$5,868.60

Sq. Hill BP Assoc. Forbes & Murray

$22,000.00

 

$22,000.00

JDE Job # 0141008012

$134,924.55

$0.00

$134,924.55