Title: Resolution authorizing the Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thirty-Two Thousand Five Hundred Four Dollars and Thirteen Cents ($1,732,504.13), a net increase of Eighty-Six Thousand Seven Hundred Thirty-Three Dollars and Seventy-Six Cents ($86,733.76), reimbursable at various rates.
Indexes: AGREEMENTS
Attachments: 1. 2026-0179 Cover Letter-Sylvan Smart - A Liberoni Supplement Letter - signed, 2. Summary 2026-0179

title

Resolution authorizing the Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thirty-Two Thousand Five Hundred Four Dollars and Thirteen Cents ($1,732,504.13), a net increase of Eighty-Six Thousand Seven Hundred Thirty-Three Dollars and Seventy-Six Cents ($86,733.76), reimbursable at various rates.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Seven Hundred Thirty-Two Thousand Five Hundred Four Dollars and Thirteen Cents ($1,732,504.13), a net increase of Eighty-Six Thousand Seven Hundred Thirty-Three Dollars and Seventy-Six Cents ($86,733.76), reimbursable at various rates.

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

PREVIOUS AMOUNT

CURRENT AMOUNT

TOTAL AMOUNT

SOURCE

6074010423

40114

2023

$1,004,502.77

$144,800.84

$1,149,303.61

FHWA

6074011623

40114

2023

$73,241.48

($8,363.04)

$64,878.44

PWSA

6075050219

40019

2019

$568,026.12

($49,704.04)

$518,322.08

Bond

Total:

 

 

$1,645,770.37

$86,733.76