Title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Utility, Right of Way and Construction Phases of the Swinburne Bridge project, and providing for the payment of costs thereof, not to exceed Fifteen Million Four Hundred Thousand Dollars ($15,400,000.00), an increase of Four Hundred Ninety-One Thousand Dollars ($491,000.00) from the previously passed authorization; reimbursable at Ninety Five percent; and the municipal share of Commonwealth Incurred Costs not to exceed Sixteen Thousand Two Hundred and Fifty Dollars ($16,250.00).
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1: The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Utility, Right of Way and Construction Phases of the Swinburne Bridge project, and providing for the payment of costs thereof, not to exceed Fifteen Million Four Hundred Thousand Dollars ($15,400,000.00), an increase of Four Hundred Ninety-One Thousand Dollars ($491,000.00) from the previously passed authorization; reimbursable at Ninety Five percent;
Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
Previous Amount
Current Amount
Total Amount
SOURCE
Preliminary
6030180218
40017
2018
$40,000.00
$40,000.00
Bond
Design
6030180018
40114
2018
$760,000.00
$760,000.00
FHWA/SHWA
6073850119
40019
2019
$16,398.00
$16,398.00
Bond
6073850219
40114
2019
$335,054.00
$335,054.00
FHWA/SHWA
6073850722
40022
2022
$9,052.00
$24,550.00
$33,602.00
Bond
6073850822
40114
2022
$148,496.00
$466,450.00
$614,946.00
FHWA/SHWA
Final Design
6030180218
40017
2018
$3,500.00
-$3,500.00
$-
Bond
6030180018
40114
2018
$90,000.00
-$90,00...
Click here for full text