Title: Resolution providing for an Agreement or Agreements with H.W. Lochner, Inc. for costs associated with the Preliminary Design Phase for the Pittsburgh City Steps project; providing for the payment of the costs thereof, not to exceed Six Hundred Sixty-Nine Thousand Eight Hundred Fifty Dollars and Seventy-Eight Cents ($669,850.78), reimbursable at eighty (80%) percent.
Indexes: AGREEMENTS
Attachments: 1. 2024-1340 Cover Letter-Pgh City Steps H.W. Lochner Letter - signed, 2. Summary 2024-1340

title

Resolution providing for an Agreement or Agreements with H.W. Lochner, Inc. for costs associated with the Preliminary Design Phase for the Pittsburgh City Steps project; providing for the payment of the costs thereof, not to exceed Six Hundred Sixty-Nine Thousand Eight Hundred Fifty Dollars and Seventy-Eight Cents ($669,850.78), reimbursable at eighty (80%) percent.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements with H.W. Lochner, Inc. for costs associated with the Preliminary Design Phase for the Pittsburgh City Steps project; providing for the payment of the costs thereof, not to exceed Six Hundred Sixty-Nine Thousand Eight Hundred Fifty Dollars and Seventy-Eight Cents ($669,850.78), to be paid from the following accounts:

 

Project

JDE JOB NO.

JDE FUND

BUDGET YEAR

TOTAL AMOUNT

SOURCE

Pittsburgh City Steps PE

6000360524

40114

2024

$535,880.62

TIP

 

6000360424

40024

2024

$133,970.16

Bond

 

 

 

TOTAL

$669,850.78