Title: Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project, and providing for the payment of costs thereof, not to exceed Four Million Seven Hundred Forty-Eight Thousand Five Hundred Fifty-Six Dollars ($4,748,556.00), an increase of Four Hundred Thirty-Seven Thousand Six Hundred Three Dollars ($437,603.00) from the previously passed authorization, reimbursable at one hundred percent.
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2024-1019 Cover Letter-South Side Signals RA Amend 6 Letter - signed, 2. Summary 2024-1019

title

Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project, and providing for the payment of costs thereof, not to exceed Four Million Seven Hundred Forty-Eight Thousand Five Hundred Fifty-Six Dollars ($4,748,556.00), an increase of Four Hundred Thirty-Seven Thousand Six Hundred Three Dollars ($437,603.00) from the previously passed authorization, reimbursable at one hundred percent.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project, and providing for the payment of costs thereof, not to exceed Four Million Seven Hundred Forty-Eight Thousand Five Hundred Fifty-Six Dollars ($4,748,556.00), an increase of Four Hundred Thirty-Seven Thousand Six Hundred Three Dollars ($437,603.00), reimbursable at one hundred percent.

 

 

Phase

JDE Fund

JDE Job No.

Budget Year

Source

Previous Amount

Current Amount

Total Amount

Construction

40114

6071180121

2021

FHWA

$4,310,953.00

$437,603.00

$4,748,556.00

 

 

 

 

TOTAL

$4,310,953.00

$437,603.00

$4,748,556.00

 

 

Section 2.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Construction phase of the South Side Signals project at no cost ($0.00) to the City of Pittsburgh.