Pittsburgh Logo
File #: 2023-1876    Version: 1
Type: Resolution Status: Passed Finally
File created: 9/1/2023 In control: Committee on Public Works and Infrastructure
On agenda: 9/6/2023 Final action: 9/19/2023
Enactment date: 9/19/2023 Enactment #: 597
Effective date: 9/22/2023    
Title: Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Utility, Right of Way and Construction Phases of the Swinburne Street Bridge project, and providing for the payment of costs thereof, not to exceed Fourteen Million Nine Hundred and Nine Thousand Dollars ($14,909,000.00), an increase of Twelve Million Five Hundred and Fifty Nine Thousand Dollars ($12,559,000.00) from the previously executed agreement (52622-2); reimbursable at Ninety Five percent; and the municipal share of Commonwealth Incurred Costs not to exceed Sixteen Thousand Two Hundred and Fifty Dollars ($16,250.00), a Twelve Thousand Two Hundred and Fifty Dollar ($12,250.00) increase from the previously executed agreement (52622-2).
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2023-1876 Cover Letter Swinburne Bridge RA Letter - signed, 2. Summary 2023-1876
title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Utility, Right of Way and Construction Phases of the Swinburne Street Bridge project, and providing for the payment of costs thereof, not to exceed Fourteen Million Nine Hundred and Nine Thousand Dollars ($14,909,000.00), an increase of Twelve Million Five Hundred and Fifty Nine Thousand Dollars ($12,559,000.00) from the previously executed agreement (52622-2); reimbursable at Ninety Five percent; and the municipal share of Commonwealth Incurred Costs not to exceed Sixteen Thousand Two Hundred and Fifty Dollars ($16,250.00), a Twelve Thousand Two Hundred and Fifty Dollar ($12,250.00) increase from the previously executed agreement (52622-2).

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Utility, Right of Way and Construction Phases of the Swinburne Street Bridge project, and providing for the payment of costs thereof, not to exceed Fourteen Million Nine Hundred and Nine Thousand Dollars ($14,909,000.00), an increase of Twelve Million Five Hundred and Fifty Nine Thousand Dollars ($12,559,000.00) from the previously executed agreement (52622-2); reimbursable at Ninety Five percent;


Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
Previous Amount
Current Amount
Total Amount
SOURCE
Preliminary
6030180218
40017
2018
$36,500.00
$3,500.00
$40,000.00
Bond
Design
6030180018
40114
2018
$670,000.00
$90,000.00
$760,000.00
FHWA/SHWA

6073850119
40019
2019
$16,000.00
$398.00
$16,398.00
Bond

6073850219
40114
2019
$327,500.00
$7,554.00
$335,054...

Click here for full text