Title: Resolution amending Resolution 657 of 2025 authorizing the Mayor and the Director of the Department of Public Works to enter into an Agreement or Agreements with Tree Pittsburgh for a restoration project known as "Rising Main 3" consisting of a deforested corridor in Highland Park, at a City cost not to exceed Two Hundred Seventy-Five Thousand Two Hundred Fifty-Seven Dollars and Four Cents ($275,257.04) over a period of five (5) years, by revising the payment schedule over a period of four (4) years.
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2026-0299 Cover Letter-DPW Letter to Council Amend1, Rising Main 3 Project - Tree Pittsburgh - signed, 2. 2026-0299 -EORC Waiver Letter, Highland Park Rising Main 3 - Tree Pittsburgh 2026, 3. 2026-0299 -Highland_Park_Rising_Main_3_Restoration_(Addendum_#2_Revision) - RFP, 4. Summary 2026-0299

title

Resolution amending Resolution 657 of 2025 authorizing the Mayor and the Director of the Department of Public Works to enter into an Agreement or Agreements with Tree Pittsburgh for a restoration project known as “Rising Main 3” consisting of a deforested corridor in Highland Park, at a City cost not to exceed Two Hundred Seventy-Five Thousand Two Hundred Fifty-Seven Dollars and Four Cents ($275,257.04) over a period of five (5) years, by revising the payment schedule over a period of four (4) years.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Resolution 657 of 2025 entitled “Resolution authorizing the Mayor and the Director of the Department of Public Works to enter into an Agreement or Agreements with Tree Pittsburgh for a restoration project known as “Rising Main 3” consisting of a deforested corridor in Highland Park, at a City cost not to exceed Two Hundred Seventy-Five Thousand Two Hundred Fifty-Seven Dollars and Four Cents ($275,257.04) over a period of five (5) years” is hereby amended as follows:

 

Section 1.  The Mayor and the Director of the Department of Public Works are hereby authorized to enter into an Agreement or Agreements with Tree Pittsburgh for a restoration project known as “Rising Main 3” consisting of a deforested corridor in Highland Park, at a City cost not to exceed Two Hundred Seventy-Five Thousand Two Hundred Fifty-Seven Dollars and Four Cents ($275,257.04) over a period of four (4) years, chargeable and payable from the Shade Tree Trust Fund as follows:

 

Year

Amount

Account

2026

$167,867.88

4000285300.57103.00

2027

$80,029.71

4000285300.57103.00

2028

$11,079.73

4000285300.57103.00

2029

$16,279.73

4000285300.57103.00

 

Section 2.  Said Agreement or Agreements thereto shall be approved by the City Solicitor as to form.