File #: 2025-2581    Version: 1
Type: Resolution Status: Reported from Standing Committee
File created: 11/26/2025 In control: Committee on Public Works and Infrastructure
On agenda: 12/2/2025 Final action:
Enactment date: Enactment #:
Effective date:    
Title: Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, and Right-of-Way phases of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed One Million Four Hundred Thousand Dollars ($1,400,000.00), an increase of Seven Hundred Fifty Thousand Dollars ($750,000.00) from the previously executed agreement, federally reimbursable at 100%. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2025-2581 Cover Letter-Elizabeth Street Bridge RA Amend 2 Letter - signed, 2. Summary 2025-2581
title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, and Right-of-Way phases of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed One Million Four Hundred Thousand Dollars ($1,400,000.00), an increase of Seven Hundred Fifty Thousand Dollars ($750,000.00) from the previously executed agreement, federally reimbursable at 100%. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, and Right-of-Way phases of the Elizabeth Street Bridge Rehabilitation Project; providing for the payment of the costs thereof, not to exceed One Million Four Hundred Thousand Dollars ($1,400,000.00), an increase of Seven Hundred Fifty Thousand Dollars ($750,000.00) from the previously executed agreement, federally reimbursable at 100%, to be paid from the following account/s:

Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
PREVIOUS AMOUNT
CURRENT AMOUNT
TOTAL AMOUNT
SOURCE
Preliminary Design
6031100122
40114
2022
$352,000.00
-
$352,000.00
FHWA

6031100123
40114
2023
$298,000.00
-
$298,000.00
FHWA
Final Design
6031100224
40114
2024
-
$475,000.00
$475,000.00
FHWA

6031100126
40114
2026
-
$225,000.00
$225,000.00
FHWA
Right of Way
6031100424
40114
2024
-
$47,500.00
$47,500.00
FHWA

6031100226
40114
2026
-
$2,500.00
$2,500.00
FHWA



TOTAL
$650,000...