Title
Resolution authorizing the Mayor and the Director of the Department of Public Works, to enter into an Agreement or Agreements, or the use of existing Agreements, between the City of Pittsburgh and Pashek + MTR, for the professional landscape architectural services for South Side Park Phase I Design at a cost not to exceed Three Hundred Thirty Eight Thousand Ninety Six Dollars (338,096.00).
Body
WHEREAS, a planning process with residents and stakeholders in the communities surrounding South Side Park resulted in the Department of City Planning to develop a Master Plan for South Side Park; and
WHEREAS, the City of Pittsburgh 2019 Capital Budget includes $400,000.00 for South Side Park Phase I Design; and
WHEREAS, on April 1, 2019, the Office of Management and Budget, on behalf of the Department of Public Works, released a Request for Proposals to solicit for landscape architectural services for professional services to complete design documents for Phase I; and
WHEREAS, a selection committee chose a proposal by Pashek + MTR for professional landscape architectural services.
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of Public Works, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements, or the use of existing Agreements, for the professional landscape architectural services for South Side Park Phase I Design between the City of Pittsburgh and Pashek + MTR. The total not to exceed cost is Three Hundred Thirty Eight Thousand Ninety Six Dollars ($338,096.00), for professional services.
Funds are available in the Park Reconstruction (BOND) line item, 2019 DELIVERABLE:
South Side Park - Phase I Design Documents
JDE Fund |
JDE Job. No. |
Budget Year |
Amount |
Source |
Account No. |
Item No. |
40019 |
4550000519 |
2019 |
$338,096.00 |
BOND |
54205 |
1419 |