Pittsburgh Logo
File #: 2024-0560    Version: 1
Type: Resolution Status: Passed Finally
File created: 5/31/2024 In control: Committee on Public Works and Infrastructure
On agenda: 6/4/2024 Final action: 6/18/2024
Enactment date: 6/18/2024 Enactment #: 420
Effective date: 6/19/2024    
Title: Resolution providing amending Resolution 61 of 2024 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00) for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Six Thousand Two Hundred Fifty Dollars ($6,250.00) Seven Thousand One Hundred Dollars ($7,100.00), an increase of Eight Hundred Fifty Dollars ($850.00) from the previously executed agreement for costs associated with the Preliminary Engineering and Final Design phases of the project. Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2024-0560 Cover letter Charles Anderson RA Amend Letter 5 - signed, 2. 2024-0560 Agreement-R15110021-5, 3. Summary 2024-0560
title
Resolution providing amending Resolution 61 of 2024 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00) for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Six Thousand Two Hundred Fifty Dollars ($6,250.00) Seven Thousand One Hundred Dollars ($7,100.00), an increase of Eight Hundred Fifty Dollars ($850.00) from the previously executed agreement for costs associated with the Preliminary Engineering and Final Design phases of the project. Future Resolutions will authorize the project specific service agreements.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00), an increase of Six Million Two Hundred Thousand Dollars ($6,200,000.00) for costs associated with the Construction phase of the project from the previously executed agreement, to be paid from the following account/s:


Phase
Job Number
Fund
Year
Previous Amount
Current Amount
Total Amount
Source
Preliminary Engineering
4430133016
40114
2016
$37,500.00

$37,500.00
Bond
Preliminary Engineering
4430133016
40114
2016
$712,500.00

$712,500.00
FHWA/SHWA
Preliminary Engineering
4430133017
40114
2017
$35,450.00

$35,450.00
Bond
Prelim...

Click here for full text