Title: Resolution providing for a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Smithfield Street Phase 2 – Fort Pitt Blvd to Forbes Avenue project, and providing for the payment of costs thereof, not to exceed Nine Hundred Thousand Dollars ($900,000.00), reimbursable at 80%; and the municipal share of Commonwealth Incurred Costs at a cost to the City of Pittsburgh not to exceed Six Thousand Dollars ($6,000.00).
Indexes: AGREEMENTS
Attachments: 1. 2026-1104 Cover Letter - Smithfield St Phase 2 RA letter - signed, 2. Summary 2026-1104
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Resolution providing for a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Smithfield Street Phase 2 – Fort Pitt Blvd to Forbes Avenue project, and providing for the payment of costs thereof, not to exceed Nine Hundred Thousand Dollars ($900,000.00), reimbursable at 80%; and the municipal share of Commonwealth Incurred Costs at a cost to the City of Pittsburgh not to exceed Six Thousand Dollars ($6,000.00).

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Smithfield Street Phase 2 – Fort Pitt Blvd to Forbes Avenue project, and providing for the payment of costs thereof, not to exceed Nine Hundred Thousand Dollars ($900,000.00), reimbursable at 80%, to be paid from the following account(s):

Phase
JDE Fund
JDE Job No.
Budget Year
Source
Amount

Preliminary Design
40114
6073780227
2027
FHWA
$ 720,000.00


40027
6073780127
2027
Bond
$ 180,000.00





TOTAL
$ 900,000.00



Section 2

The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Smithfield Street Phase 2 – Fort Pitt Blvd to Forbes Avenue project at a cost to the City of Pittsburgh not to exceed Six Thousand Dollars ($6,000.00).

Phase
JDE Fund
JDE Job No.
Budget Year
Source
Amount

Preliminary Design
40027
6073780127
2027
Bond
$ 6,000.00


...