Presenter
Presented by Mr. Shields
Title
Resolution providing for an Agreement or Agreements or for the use of existing Agreements, with a Consultant or Consultants, for design services and for project management services, in connection with the transformation of Penn Circle into a two-way traffic flow system; providing for a Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania; and further providing for the payment of the costs thereof. Cost not to exceed $1,800,000.00
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Engineering and Construction, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements or to use existing Agreements, in form approved by the City Solicitor, with a Consultant or Consultants for engineering services and project management services related to the transformation of Penn Circle into a two-way traffic flow system, at a cost not to exceed $1,800,000.00, chargeable to and payable from the following account:
Account 600000
Fund 2610
Org 301000
Sub-Class C2004
Project/Grant 2205901
Budget Year 2004
Amount $360,000
Source CDBG
Account 600000
Fund 5100
Org 301000
Sub-Class PGHPR
Project/Grant 2205901
Budget Year 2004
Amount $1,440,000
Source FHWA
TOTAL $1,800,000
Section 2. The Mayor and the Director of the Department of Engineering and Construction, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements, in form approved by the City Solicitor, with the Commonwealth of Pennsylvania, Department of Transportation, for the reimbursement to the City of Pittsburgh of the Federal Government's share of costs in connection with the design services for the Penn Circle Improvements.