File #: 2026-0447    Version: 1
Type: Resolution Status: Passed Finally
File created: 5/1/2026 In control: Committee on Public Works and Infrastructure
On agenda: 5/6/2026 Final action: 5/12/2026
Enactment date: 5/12/2026 Enactment #: 290
Effective date: 5/14/2026    
Title: Resolution authorizing the Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Eight Hundred Seventy-One Thousand Eight Hundred Ten Dollars and Ninety-Seven Cents ($1,871,810.97) a net increase of One Hundred Thirty-Nine Thousand Three Hundred Six Dollars and Eighty-Four Cents ($139,306.84), reimbursable at various rates.
Indexes: AGREEMENTS
Attachments: 1. 2026-0447 Cover Letter-Sylvan Smart - A Liberoni Supplement 2 Letter - signed, 2. Summary 2026-0447

title

Resolution authorizing the Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Eight Hundred Seventy-One Thousand Eight Hundred Ten Dollars and Ninety-Seven Cents ($1,871,810.97) a net increase of One Hundred Thirty-Nine Thousand Three Hundred Six Dollars and Eighty-Four Cents ($139,306.84), reimbursable at various rates.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a supplemental agreement or agreements with A. Liberoni Inc., for costs associated with construction for the Sylvan Avenue Multimodal Path Project; providing for the payment of the costs thereof, not to exceed One Million Eight Hundred Seventy-One Thousand Eight Hundred Ten Dollars and Ninety-Seven Cents ($1,871,810.97) a net increase of One Hundred Thirty-Nine Thousand Three Hundred Six Dollars and Eighty-Four Cents ($139,306.84) reimbursable at various rates.

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

PREVIOUS AMOUNT

CURRENT AMOUNT

TOTAL AMOUNT

SOURCE

6074010423

40114

2023

$1,149,303.61

$64,589.00

$1,213,892.61

FHWA

6074011623

40114

2023

$64,878.44

($37,417.69)

$27,460.75

PWSA

6075050219

40019

2019

$518,322.08

$112,135.53

$630,457.61

Bond

Total:

 

 

$1,732,504.13

$139,306.84

$1,871,810.97