Title: Resolution providing for an amended Agreement or Agreements with SAI Consulting Engineers, Inc. for costs associated with the CBD Signals Phase 4 Project; providing for payment of the costs thereof, not to exceed Six Hundred Thirty-Three Thousand Eight Hundred Eighty-Seven Dollars and Forty-Six Cents ($633,887.46), an increase of Fifty-Seven Thousand Nine Hundred Ninety-Nine Dollars and Eighty-Two Cents ($57,999.82) from the previously passed authorization (688 of 2024).
Indexes: AGREEMENTS (AMENDING)
Attachments: 1. 2024-1249 Cover Letter-CBD4 supplement amend 2 letter - signed, 2. Summary 2024-1249

title

Resolution providing for an amended Agreement or Agreements with SAI Consulting Engineers, Inc. for costs associated with the CBD Signals Phase 4 Project; providing for payment of the costs thereof, not to exceed Six Hundred Thirty-Three Thousand Eight Hundred Eighty-Seven Dollars and Forty-Six Cents ($633,887.46), an increase of Fifty-Seven Thousand Nine Hundred Ninety-Nine Dollars and Eighty-Two Cents ($57,999.82) from the previously passed authorization (688 of 2024).

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Agreement or Agreements with SAI Consulting Engineers, Inc. for costs associated with the CBD Signals Phase 4 Project; providing for payment of the costs thereof, not to exceed Six Hundred Thirty-Three Thousand Eight Hundred Eighty-Seven Dollars and Forty-Six Cents ($633,887.46), an increase of Fifty-Seven Thousand Nine Hundred Ninety-Nine Dollars and Eighty-Two Cents ($57,999.82) from the previously passed authorization (688 of 2024), chargeable and payable from the following account(s):

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

PREVIOUS AMOUNT

CURRENT AMOUNT

TOTAL AMOUNT

SOURCE

6072220221

40114

2021

$419,791.46

 

$419,791.46

FHWA

6072220222

40114

2022

$40,918.65

$46,399.86

$87,318.51

FHWA

6072220121

40021

2021

$104,947.87

 

$104,947.87

Bond

6072220122

40022

2022

$10,229.66

$11,599.96

$21,829.62

Bond

Total

 

 

$575,887.64

$57,999.82

$633,887.46