Legislation Details

File #: 2026-0925    Version: 1
Type: Resolution Status: To Be Presented
File created: 9/25/2026 In control: Committee on Public Works and Infrastructure
On agenda: 9/29/2026 Final action:
Enactment date: Enactment #:
Effective date:    
Title: Resolution providing for a Supplemental Agreement or Agreements with KCI Technologies Inc. for costs associated with Final Design phase of the 28th Street Bridge project, and providing for the payment of costs thereof, not to exceed Two Million Three Hundred Twenty Thousand Five Hundred Eighty-One Dollars and Fourteen Cents ($2,320,581.14), an increase of Sixty-Two Thousand Fifty-Seven Dollars and Twenty-Eight Cents ($62,057.28) from the previously executed agreement, reimbursable at 95%.
Indexes: AGREEMENTS
Attachments: 1. 2026-0925 Cover Letter-28th St Bridge - KCI FD Sup Letter - signed, 2. Summary 2026-0925
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Resolution providing for a Supplemental Agreement or Agreements with KCI Technologies Inc. for costs associated with Final Design phase of the 28th Street Bridge project, and providing for the payment of costs thereof, not to exceed Two Million Three Hundred Twenty Thousand Five Hundred Eighty-One Dollars and Fourteen Cents ($2,320,581.14), an increase of Sixty-Two Thousand Fifty-Seven Dollars and Twenty-Eight Cents ($62,057.28) from the previously executed agreement, reimbursable at 95%.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a supplemental agreement or agreements with KCI Technologies Inc. for costs associated with Final Design phase of the 28th Street Bridge project, and providing for the payment of costs thereof, not to exceed Two Million Three Hundred Twenty Thousand Five Hundred Eighty-One Dollars and Fourteen Cents ($2,320,581.14), an increase of Sixty-Two Thousand Fifty-Seven Dollars and Twenty-Eight Cents ($62,057.28) from the previously executed agreement; chargeable and payable from the following accounts:


JDE Job No.
JDE Fund
Budget Year
PREVIOUS AMOUNT
CURRENT AMOUNT
TOTAL AMOUNT
Source

6030210019
40114
2019
$827,180.38
-
$827,180.38
FHWA/SHWA

6030209019
40019
2019
$42,035.82
-
$42,035.82
Bond

6008810220
40114
2020
$138,905.85
-
$138,905.85
FHWA/SHWA

6008810120
40020
2020
$6,620.88
-
$6,620.88
Bond

6073870222
40114
2022
$2,189.95
-
$2,189.95
Bond

6008810421
40114
2021
$123,500.00
-
$123,500.00
FHWA/SHWA

6008810321
40021
2021
$6,500.00
-
$6,500.00
Bond

6008810222
40114
2022
$576,967.29
-
$576,967.29
FHWA/SHWA

6008810122
40022
2022
$27,866.70
-
$27,866.70
Bond

6008810224
40114
2024
$437,000.00
-
$437,000.00
FHWA/SHWA

6008810124
40024
2024
$23,000.00
...

Click here for full text