File #: 2024-0305    Version: 1
Type: Resolution Status: Passed Finally
File created: 3/22/2024 In control: Committee on Public Works and Infrastructure
On agenda: 3/25/2024 Final action: 4/9/2024
Enactment date: 4/9/2024 Enactment #: 243
Effective date: 4/10/2024    
Title: Resolution providing for a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bloomfield Bridge Project; providing for the payment of the costs thereof, not to exceed One Million Two Hundred Thousand Dollars ($1,200,000.00), reimbursable at 100%. This resolution serves to authorize only the Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS
Attachments: 1. 2024-0305 Cover Letter Bloomfield Bridge RA Letter - signed, 2. Summary 2024-0305

Title

Resolution providing for a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bloomfield Bridge Project; providing for the payment of the costs thereof, not to exceed One Million Two Hundred Thousand Dollars ($1,200,000.00), reimbursable at 100%. This resolution serves to authorize only the Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh.  Future Resolutions will authorize the project specific service agreements.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bloomfield Bridge Project; providing for the payment of the costs thereof, not to exceed One Million Two Hundred Thousand Dollars ($1,200,000.00) to be paid from the following accounts:

 

Phase

JDE JOB NO.

JDE FUND

BUDGET YEAR

AMOUNT

SOURCE

Preliminary Design

6031160124

40114

2024

$1,200,000.00

FHWA

 

 

 

TOTAL

$1,200,000.00

 

 

Section 2

 

The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania, Department of Transportation for the Preliminary Design phase of the Bloomfield Bridge Project at no cost to the City of Pittsburgh: