File #:
|
2026-0302
Version:
1
|
|
|
|
Type:
|
Resolution
|
Status:
|
In Standing Committee
|
|
On agenda:
|
3/31/2026
|
Final action:
|
|
|
Enactment date:
|
|
Enactment #:
|
|
|
Title:
|
Resolution providing for a supplemental agreement or agreements with MS Consultants, Inc. for costs associated with the Preliminary Engineering and Final Design phases of the California Avenue Bridge project; providing for the payment of the costs thereof, not to exceed Two Million Two Hundred Five Thousand Six Hundred Ninety-Two Dollars and Ninety-Six Cents ($2,205,692.96), an increase of One Million Three Hundred Sixty Thousand Eight Hundred Ninety-Six Dollars and Ninety-Five Cents ($1,360,896.95) from the previously authorized agreement, reimbursable at 100%.
|
title
Resolution providing for a supplemental agreement or agreements with MS Consultants, Inc. for costs associated with the Preliminary Engineering and Final Design phases of the California Avenue Bridge project; providing for the payment of the costs thereof, not to exceed Two Million Two Hundred Five Thousand Six Hundred Ninety-Two Dollars and Ninety-Six Cents ($2,205,692.96), an increase of One Million Three Hundred Sixty Thousand Eight Hundred Ninety-Six Dollars and Ninety-Five Cents ($1,360,896.95) from the previously authorized agreement, reimbursable at 100%.
body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a supplemental agreement or agreements with MS Consultants, Inc. for costs associated with the Preliminary Engineering and Final Design phases of the California Avenue Bridge project; providing for the payment of the costs thereof, not to exceed Two Million Two Hundred Five Thousand Six Hundred Ninety-Two Dollars and Ninety-Six Cents ($2,205,692.96), an increase of One Million Three Hundred Sixty Thousand Eight Hundred Ninety-Six Dollars and Ninety-Five Cents ($1,360,896.95) from the previously authorized agreement, reimbursable at 100%, to be paid from the following accounts:
|
Phase |
JDE JOB NO. |
JDE FUND |
BUDGET YEAR |
PREVIOUS AMOUNT |
CURRENT AMOUNT |
TOTAL AMOUNT |
SOURCE |
|
Preliminary Engineering |
6031080122 |
40114 |
2022 |
$670,163.64 |
|
$670,163.64 |
FHWA |
|
Preliminary Engineering |
6031080123 |
40114 |
2023 |
$174,632.37 |
($113,000.00) |
$61,632.37 |
FHWA |
|
Final Design |
6031080126 |
40114 |
2026 |
- |
$1,473,896.95 |
$1,473,896.95 |
FHWA |
|
|
Total: |
$844,796.01 |
$1,360,896.95 |
$2,205,692.96 |
|
|