title
Resolution providing for an amended Agreement for Construction services with S.E.T., Inc. for the South Side Signals project at a cost thereof, not to exceed Three Million Eight Hundred Twenty-Two Thousand Three Hundred Thirty-Five Dollars and Ninety-Six Cents ($3,822,335.96), an increase of Five Hundred Forty-Two Thousand Three Hundred Thirty-Five Dollars and Ninety-Six Cents ($542,335.96) from the previously legislated contract authorization (142 of 2022).
body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended agreement with S.E.T., Inc. for Construction services for the South Side Signals project; and providing for the payment of the costs thereof, not to exceed Three Million Eight Hundred Twenty-Two Thousand Three Hundred Thirty-Five Dollars and Ninety-Six Cents ($3,822,335.96), an increase of Five Hundred Forty-Two Thousand Three Hundred Thirty-Five Dollars and Ninety-Six Cents ($542,335.96) from the previously legislated contract authorization (142 of 2022);
JDE JOB NO. |
JDE FUND |
Budget Year |
Previous Authorization |
Additional Authorization |
Total Authorization |
Source |
6071180121 |
40114 |
2021 |
$3,216,820.00 |
$540,312.39 |
$3,757,132.39 |
FHWA |
6071180120 |
40020 |
2020 |
$ 63,180.00 |
$2,023.57 |
$65,203.57 |
Bond |
Total |
|
|
$3,280,000.00 |
$542,335.96 |
$3,822,335.96 |
|
Section 2. The agreements or agreements and amendments are subject to the approval of the City Solicitor as to form.