Title: Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a cost not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00). Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS
Attachments: 1. 2023-1663 Cover Letter-Parking Lot Bridge RA Letter - signed, 2. Summary 2023-1663
title
Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a cost not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00). Future Resolutions will authorize the project specific service agreements.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00) to be paid from the following accounts:


Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
AMOUNT
SOURCE
Preliminary Design
6031090223
40114
2023
$593,750.00
FHWA

6031090123
40023
2023
$31,250.00
BOND



TOTAL
$625,000.00



Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Commonwealth of Pennsylvania, Department of Transportation for the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project providing for the payment of the costs thereof, not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00), to be paid from the following account:


Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
AMOUNT...