Title: Resolution providing for an Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Forty-Eight Million Four Hundred Seventy-Seven Thousand Seven Hundred Seventy-Seven Dollars ($48,477,777.00), reimbursable at 100%.
Indexes: AGREEMENTS
Attachments: 1. 2024-0243 Cover Letter-Charles Anderson Mosites - CON - signed, 2. Summary 2024-0243

Title

Resolution providing for an Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Forty-Eight Million Four Hundred Seventy-Seven Thousand Seven Hundred Seventy-Seven Dollars ($48,477,777.00), reimbursable at 100%.

 

Body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Forty-Eight Million Four Hundred Seventy-Seven Thousand Seven Hundred Seventy-Seven Dollars ($48,477,777.00), reimbursable at 100%.

 

JDE JOB NO.

JDE FUND

BUDGET YEAR

TOTAL AMOUNT

SOURCE

6073810123

40114

2023

$11,100.00

PWSA

6073810224

40114

2024

$44,556,590.89

FHWA

6073810225

40114

2025

$3,910,086.11

FHWA

Total:

 

 

$48,477,777.00