Legislation Details
|
File #:
|
2026-1077
Version:
1
|
|
|
|
Type:
|
Resolution
|
Status:
|
To Be Presented
|
|
On agenda:
|
11/2/2026
|
Final action:
|
|
|
Enactment date:
|
|
Enactment #:
|
|
|
Title:
|
Resolution providing for an amended Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Sixty Million Two Hundred Seventy-One Thousand Seven Hundred Eighty-Two Dollars and Seven Cents ($60,271,782.07), an increase of Eleven Million Seven Hundred Ninety-Four Thousand Five Dollars and Seven Cents ($11,794,005.07) from the previously executed agreement, reimbursable at 100%.
|
|
Indexes:
|
AGREEMENTS (AMENDING)
|
title
Resolution providing for an amended Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Sixty Million Two Hundred Seventy-One Thousand Seven Hundred Eighty-Two Dollars and Seven Cents ($60,271,782.07), an increase of Eleven Million Seven Hundred Ninety-Four Thousand Five Dollars and Seven Cents ($11,794,005.07) from the previously executed agreement, reimbursable at 100%.
body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Agreement or Agreements with Mosites Construction Company for costs associated with construction of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Sixty Million Two Hundred Seventy-One Thousand Seven Hundred Eighty-Two Dollars and Seven Cents ($60,271,782.07), an increase of Eleven Million Seven Hundred Ninety-Four Thousand Five Dollars and Seven Cents ($11,794,005.07) from the previously executed agreement, reimbursable at 100%.
|
JDE JOB NO. |
JDE FUND |
BUDGET YEAR |
PREVIOUS AMOUNT |
CURRENT AMOUNT |
TOTAL AMOUNT |
SOURCE |
|
6073810123 |
40114 |
2023 |
$11,100.00 |
- |
$11,100.00 |
PWSA |
|
6073810224 |
40114 |
2024 |
$44,556,590.89 |
- |
$44,556,590.89 |
FHWA |
|
6073810225 |
40114 |
2025 |
$3,910,086.11 |
$6,622,548.24 |
$10,532,634.35 |
FHWA |
|
6073810126 |
40114 |
2026 |
- |
$5,171,456.83 |
$5,171,456.83 |
FHWA |
|
Total: |
|
|
$48,477,777.00 |
$11,794,005.07 |
$60,271,782.07 |
|
|