File #: 2025-2525    Version: 1
Type: Resolution Status: To Be Presented
File created: 11/21/2025 In control: Committee on Public Works and Infrastructure
On agenda: 11/24/2025 Final action:
Enactment date: Enactment #:
Effective date:    
Title: Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, and Right-of-Way phases of the California Ave Bridge Project; providing for the payment of the costs thereof, not to exceed Three Million One Hundred Twenty Thousand Dollars ($3,120,000.00), an increase of Two Million One Hundred Thousand Dollars ($2,100,000.00) from the previously executed agreement. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS (AMENDING), RIGHT OF WAY
Attachments: 1. 2025-2525 Cover Letter-California Ave Bridge RA Amend 2 Letter - signed, 2. Summary 2025-2525
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, and Right-of-Way phases of the California Ave Bridge Project; providing for the payment of the costs thereof, not to exceed Three Million One Hundred Twenty Thousand Dollars ($3,120,000.00), an increase of Two Million One Hundred Thousand Dollars ($2,100,000.00) from the previously executed agreement. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at no cost to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.

body
Be it resolved by the Council of the City of Pittsburgh as follows:

Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, and Right-of-Way phases of the California Ave Bridge Project; providing for the payment of the costs thereof, not to exceed Three Million One Hundred Twenty Thousand Dollars ($3,120,000.00), an increase of Two Million One Hundred Thousand Dollars ($2,100,000.00) from the previously executed agreement, to be paid from the following accounts:

Phase
JDE JOB NO.
JDE FUND
BUDGET YEAR
PREVIOUS AMOUNT
CURRENT AMOUNT
TOTAL AMOUNT
SOURCE
Preliminary Design
6031080122
40114
2022
$800,000.00
-
$800,000.00
FHWA

6031080123
40114
2023
$220,000.00
-
$220,000.00
FHWA
Final Design
6031080126
40114
2026
-
$2,000,000.00
$2,000,000.00
FHWA
Right of Way
6031080226
40114
2026
-
$100,000.00
$100,000.00
FHWA



TOTAL
$1,020,000.00
$2,100,000.00
$3,120,000.00



Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby author...