File #:
|
2025-1665
Version:
1
|
|
|
Type:
|
Resolution
|
Status:
|
In Standing Committee
|
On agenda:
|
3/25/2025
|
Final action:
|
|
Enactment date:
|
|
Enactment #:
|
|
Title:
|
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, Right of Way, and Construction phases of the Liberty Ave Highway Safety Improvement Program (HSIP); providing for the payment of the costs thereof, not to exceed Twelve Million Nine Hundred Five Thousand Five Hundred Fifty-Six Dollars ($12,905,556.00) an increase of Five Million Four Hundred Thousand Dollars ($5,400,000.00) from the previously authorized amount; and the municipal share of Commonwealth Incurred Costs not to exceed Twenty-Nine Thousand Seven Hundred Dollars ($29,700.00), an increase of Twenty Four Thousand Two Hundred Dollars ($24,200.00) from the previously authorized amount (600 of 2023). Future Resolutions will authorize the project specific agreements.
|
Indexes:
|
AGREEMENTS (AMENDING)
|
Title
Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, Right of Way, and Construction phases of the Liberty Ave Highway Safety Improvement Program (HSIP); providing for the payment of the costs thereof, not to exceed Twelve Million Nine Hundred Five Thousand Five Hundred Fifty-Six Dollars ($12,905,556.00) an increase of Five Million Four Hundred Thousand Dollars ($5,400,000.00) from the previously authorized amount; and the municipal share of Commonwealth Incurred Costs not to exceed Twenty-Nine Thousand Seven Hundred Dollars ($29,700.00), an increase of Twenty Four Thousand Two Hundred Dollars ($24,200.00) from the previously authorized amount (600 of 2023). Future Resolutions will authorize the project specific agreements.
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, Right of Way, and Construction phases of the Liberty Ave Highway Safety Improvement Program (HSIP); providing for the payment of the costs thereof, not to exceed Twelve Million Nine Hundred Five Thousand Five Hundred Fifty-Six Dollars ($12,905,556.00) an increase of Five Million Four Hundred Thousand Dollars ($5,400,000.00) from the previously authorized amount. Funding increase to the Right of Way and Construction phases to be as through the following account/s:
PHASE |
JDE JOB NO. |
JDE FUND |
BUDGET YEAR |
AMOUNT |
SOURCE |
Right of Way |
6090100425 |
40114 |
2025 |
$480,000.00 |
FHWA |
|
6090100325 |
40025 |
2025 |
$120,000.00 |
Bond |
Construction |
6090100224 |
40114 |
2024 |
$1,896,000.00 |
FHWA |
|
6090100225 |
40114 |
2025 |
$1,987,333.30 |
FHWA |
|
6090100124 |
40024 |
2024 |
$474,000.00 |
Bond |
|
6090100125 |
40025 |
2025 |
$442,666.70 |
Bond |
|
|
|
Total |
$5,400,000.00 |
|
Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, Right of Way, and Construction phases of the Liberty Ave Highway Safety Improvement Program (HSIP), at a cost to the City of Pittsburgh not to exceed Twenty Nine Thousand Seven Hundred Dollars ($29,700.00), an increase of Twenty Four Thousand Two Hundred Dollars ($24,200.00) from the previously authorized amount, to be paid from the following accounts:
Phase |
JDE Job No. |
JDE FUND |
Budget Year |
Previous Amount |
Current Amount |
Total Amount |
Source |
Preliminary Engineering |
6030178218 |
40017 |
2018 |
$500.00 |
- |
$500.00 |
BOND |
Final Design |
6030178418 |
40017 |
2018 |
$3,000.00 |
- |
$3,000.00 |
BOND |
Right of Way |
6030178518 |
40017 |
2018 |
$1,000.00 |
- |
$1,000.00 |
BOND |
Construction |
6090100123 |
40023 |
2023 |
$1,000.00 |
$24,200.00 |
$25,200.00 |
BOND |
|
|
|
TOTAL |
$5,500.00 |
$24,200.00 |
$29,700.00 |
|
|