File #:
|
2023-1706
Version:
1
|
|
|
Type:
|
Resolution
|
Status:
|
Passed Finally
|
On agenda:
|
7/11/2023
|
Final action:
|
8/1/2023
|
Enactment date:
|
8/1/2023
|
Enactment #:
|
502
|
Title:
|
Resolution further amending Resolution No. 647 of 2020, effective December 23, 2020, as amended, entitled "Resolution adopting and approving the 2021 Capital Budget and the 2021 Community Development Block Grant Program, and the 2021 through 2026 Capital Improvement Program" by increasing Bridge Upgrades by $928,290.01, increasing Capital Equipment Acquisition by $219,833.99, reducing Complete Streets by $1,500,000.00, reducing Facility Improvements - Recreation and Senior Centers by $264,124.88, reducing Information Systems Modernization by $35,875.12, and increasing Public Safety Equipment by $651,876.00.
(Public Hearing held 8/1/23)
|
Indexes:
|
CAPITAL BUDGET (AMENDING)
|
title
Resolution further amending Resolution No. 647 of 2020, effective December 23, 2020, as amended, entitled “Resolution adopting and approving the 2021 Capital Budget and the 2021 Community Development Block Grant Program, and the 2021 through 2026 Capital Improvement Program” by increasing Bridge Upgrades by $928,290.01, increasing Capital Equipment Acquisition by $219,833.99, reducing Complete Streets by $1,500,000.00, reducing Facility Improvements - Recreation and Senior Centers by $264,124.88, reducing Information Systems Modernization by $35,875.12, and increasing Public Safety Equipment by $651,876.00.
(Public Hearing held 8/1/23)
body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. Resolution No. 647 of 2020, effective December 23, 2020, as amended, which presently reads as per Current Budget Amount, is hereby further amended to read as per Revised Budget Amount:
Fund |
Job |
Project |
Deliverable |
Dept. |
Current Budget Amount |
Change |
Revised Budget Amount |
41121 |
6031011021 |
Bridge Upgrades |
Davis Avenue Pedestrian Bridge |
DOMI |
$0.00 |
$928,290.01 |
$928,290.01 |
41121 |
8458990421 |
Capital Equipment Acquisition |
Green Fleet Improvements |
OMB |
$7,606,000.00 |
$219,833.99 |
$7,825,833.99 |
41121 |
6074011721 |
Complete Streets |
Hill District Corridor Enhancements |
DOMI |
$1,500,000.00 |
-$1,500,000.00 |
$0.00 |
41121 |
4550101721 |
Facility Improvements - Recreation and Senior Centers |
Paulson Rec Center - Facility Upgrades |
Public Works |
$300,000.00 |
-$300,000.00 |
$0.00 |
41121 |
4550102021 |
Facility Improvements - Recreation and Senior Centers |
Public Works Data Infrastructure Upgrades |
Public Works |
$0.00 |
$35,875.12 |
$35,875.12 |
41121 |
1010030721 |
Information Systems Modernization |
Paulson Rec Center - Tech Upgrades |
Public Works |
$30,526.00 |
-$5,349.12 |
$25,176.88 |
41121 |
1010030421 |
Information Systems Modernization |
Robert E. Williams Rec Center - Tech Upgrades |
Public Works |
$30,526.00 |
-$30,526.00 |
$0.00 |
41121 |
2175580121 |
Public Safety Equipment |
Interoperable Communications and Radio System |
Public Safety |
$0.00 |
$651,876.00 |
$651,876.00 |
|