title
Ordinance amending the Pittsburgh Code of Ordinances, Title 13: Stormwater Management, to correct numerous Code and statutory references and to make certain corrective text amendments.
body
WHEREAS, the City of Pittsburgh recently changed providers for public print, display, and publication of the City Code of Ordinances; and
WHEREAS, in conjunction with that transition, the City Clerk commissioned a review of the City Code of Ordinances for correction of statutory citations, technical errors, and typographical mistakes; and
WHEREAS, that review resulted in hundreds of proposed revisions to the City Code of Ordinances, improving the accuracy, readability, and uniformity of the text; and
WHEREAS, the Council of the City of Pittsburgh wishes to now adopt these revisions into the City Code of Ordinances via a series of separate ordinances amending one title at a time.
The Council of the City of Pittsburgh hereby enacts as follows:
Section 1. Title 13, Stormwater Management, shall be amended as follows:
A. Chapter 1301, General Provisions.
(1) Section 1301.03 - Purpose, is amended as indicated:
The purpose of this Title is to promote health, safety, and welfare within the City and its watersheds by minimizing the harms and maximizing the benefits described in Section 1301.02 of this Title, through provisions designed to:
The purpose of this Title is to promote health, safety, and welfare within the City and its watersheds by minimizing the harms and maximizing the benefits described in Section 1301.02 of this Title, through provisions designed to:
…
B. Chapter 1302, Definitions.
(1) Section 1302.01.
(a) The section title is amended as indicated:
[Generally.]
(b) Subsection 16, the definition of “DESIGN STORM METHOD,” is amended as indicated:
DESIGN STORM METHOD - A method of calculating stormwater management needs, also known as Volume Control-Guideline 1 (CG-1) in the PA BMP Manual3 Manual (see § 1309.01c), requiring detailed modeling based on site conditions.
(c) Subsection 34, the definition of “FLOODWAY,” is amended as indicated:
FLOODWAY - The channel of the watercourse and those portions of the adjoining floodplains that are reasonably required to carry and discharge the 100-year flood. Unless otherwise specified, the boundary of the floodway is as identified per the Floodplain Overlay District in Title 9. In an area where no FEMA maps or studies have defined the boundary of the 100-year floodway, it is assumed-absent evidence to the contrary-that the floodway extends from the stream to fifty (50) feet from the top of the bank of the stream.
(d) Subsection 62, the definition of “REGULATED EARTH DISTURBANCE ACTIVITY,” is amended as indicated:
REGULATED EARTH DISTURBANCE ACTIVITY - Activity involving earth disturbance subject to regulation under PA Code Title 25, Chapters 92a and 102, or the Clean Streams Law.
(e) Subsection 75, the definition of “SIMPLIFIED METHOD,” is amended as indicated:
SIMPLIFIED METHOD - A method of calculating stormwater management needs, also known as Volume Control-Guideline 2 (CG-2) in the PA BMP Manual 3 Manual (see § 1309.01c), which is independent of site conditions.
C. Chapter 1303, Stormwater Management Standards.
(1) Section 1303.01 - General Requirements.
(a) Subsection b is amended as indicated:
SWM Site Plans approved by the City, in accordance with Section 1304.06 1304.05, shall be on site throughout the duration of the regulated activity.
(b) Subsection h.3 is amended as indicated:
Incorporate green infrastructure methods described in the City of Pittsburgh Stormwater Design Manual. In cases where green infrastructure is infeasible, as determined within the City of Pittsburgh Stormwater Design Manual, the SWM Site Plan shall meet the requirements in Section 1303.033 1303.03.
(2) Section 1303.03 - Volume Controls.
(a) This section is amended as indicated:
Preferred and approved stormwater BMPs, as identified in the City of Pittsburgh Stormwater Design Manual, shall be used for meeting the regulatory requirements for all regulated activities. Water volume controls shall be implemented using the Design Storm Method in subsection A a. or the Simplified Method in subsection B b. below.
…
(b) Subsection a.3 is amended as indicated:
Removal options include reuse, evaporation, transpiration, and infiltration. Demonstration of technical infeasibility for the removal of runoff shall meet infeasibility criteria thresholds established within the City of Pittsburgh Stormwater Design Manual. If removal of the runoff is deemed infeasible, and the Designated Plan Reviewer agrees, runoff shall be detained and meet water quality release rate requirements as stipulated within the City of Pittsburgh Stormwater Design Manual. Fee-in lieu payments for not meeting the volume requirement within this Chapter are provided in Section 1303.03.F 1303.03.f.
(3) Section 1303.05 - Riparian Buffers. Subsection c.1 is amended as indicated:
No use or construction within the riparian buffer shall be permitted that is inconsistent with the intent of the riparian buffer as described in Section 1303.05.A 1303.05.a.
D. Chapter 1304, Stormwater Management (SWM) Site Plan Requirements.
(1) Section 1304.01 - General Requirements. Subsection b.2 is amended as indicated:
City review and approval of a SWM Site Plan in accordance with the requirements of Section 1304.03.
(2) Section 1304.03 - Stormwater Management Site Plan. Subsection b.2 is amended as indicated:
A determination of site conditions in accordance with the City of Pittsburgh Stormwater Design Manual and DEP PA BMP Manual3 Manual (see § 1309.01c). A detailed site evaluation shall be completed for projects proposed in environmentally sensitive areas, such as but not limited to brownfields and areas with steep slopes.
E. Chapter 1308, Enforcement and Penalties.
(1) Section 1308.04 - Penalties. Subsection a is amended as indicated:
Anyone violating the provisions of this Title shall be guilty of a summary offense, and upon conviction, shall be subject to a fine consistent with current City fee and penalty schedules for each violation, recoverable with costs in accordance with § 924.04G of this Code. Each day that the violation continues shall be a separate offense and penalties shall be cumulative.
F. Chapter 1309, References.
(1) Section 1309.01, the section title is amended as indicated:
[Generally.]