Title:
|
Resolution providing amending Resolution 61 of 2024 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00) for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Six Thousand Two Hundred Fifty Dollars ($6,250.00) Seven Thousand One Hundred Dollars ($7,100.00), an increase of Eight Hundred Fifty Dollars ($850.00) from the previously executed agreement for costs associated with the Preliminary Engineering and Final Design phases of the project. Future Resolutions will authorize the project specific service agreements.
|
Indexes:
|
AGREEMENTS (AMENDING)
|
title
Resolution providing amending Resolution 61 of 2024 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00) for costs associated with the Construction phase of the project, due to this phase being 100% Federally funded. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Six Thousand Two Hundred Fifty Dollars ($6,250.00) Seven Thousand One Hundred Dollars ($7,100.00), an increase of Eight Hundred Fifty Dollars ($850.00) from the previously executed agreement for costs associated with the Preliminary Engineering and Final Design phases of the project. Future Resolutions will authorize the project specific service agreements.
body
Be it resolved by the Council of the City of Pittsburgh as follows:
Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Fifty-Nine Million Eight Hundred Ninety Thousand Dollars ($59,890,000.00), an increase of Six Million Two Hundred Thousand Dollars ($6,200,000.00) for costs associated with the Construction phase of the project from the previously executed agreement, to be paid from the following account/s:
Phase |
Job Number |
Fund |
Year |
Previous Amount |
Current Amount |
Total Amount |
Source |
Preliminary Engineering |
4430133016 |
40114 |
2016 |
$37,500.00 |
|
$37,500.00 |
Bond |
Preliminary Engineering |
4430133016 |
40114 |
2016 |
$712,500.00 |
|
$712,500.00 |
FHWA/SHWA |
Preliminary Engineering |
4430133017 |
40114 |
2017 |
$35,450.00 |
|
$35,450.00 |
Bond |
Preliminary Engineering |
4430133017 |
40114 |
2017 |
$673,550.00 |
|
$673,550.00 |
FHWA/SHWA |
Preliminary Engineering |
6073810322 |
40022 |
2022 |
$6,550.00 |
|
$6,550.00 |
Bond |
Preliminary Engineering |
6073810422 |
40114 |
2022 |
$124,450.00 |
|
$124,450.00 |
FHWA/SHWA |
Final Design |
6030133021 |
40114 |
2021 |
$1,900,000.00 |
|
$1,900,000.00 |
FHWA/SHWA |
Final Design |
6030133321 |
40017 |
2021 |
$100,000.00 |
|
$100,000.00 |
Bond |
Right of Way |
6073810222 |
40114 |
2022 |
$95,000.00 |
|
$95,000.00 |
FHWA/SHWA |
Right of Way |
6073810122 |
40022 |
2022 |
$5,000.00 |
|
$5,000.00 |
Bond |
Construction |
6073810224 |
40114 |
2024 |
|
$48,600,000.00 |
$48,600,000.00 |
FHWA/SHWA |
Construction |
6073810225 |
40114 |
2025 |
|
$7,600,000.00 |
$7,600,000.00 |
FHWA/SHWA |
|
|
|
TOTAL |
$3,690,000.00 |
$56,200,000.00 |
$59,800,000.00 |
|
Section 2. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into an amended Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania, Department of Transportation for the Charles Anderson Bridge Project; at a cost not to exceed Six Thousand Two Hundred Fifty Dollars ($6,250.00) Seven Thousand One Hundred Dollars ($7,100.00), an increase of Eight Hundred Fifty Dollars ($850.00) from the previously executed agreement for costs associated with the Preliminary Engineering and Final Design phases of the project, to be paid from the following accounts:
JDE Fund |
JDE Job No. |
Budget Year |
Previous Amount |
Current Amount |
Total Amount |
Source |
Item No. |
40114 |
4430133017 |
2017 |
$2,167.66 |
|
$2,167.66 |
BOND |
1419 |
40022 |
6073810322 |
2022 |
$1,332.34 |
$1550.00 |
$2,882.34 |
BOND |
1419 |
40017 |
6030133321 |
2021 |
$2,250.00 |
-$250.00 |
$2,000.00 |
BOND |
1419 |
40022 |
6073810122 |
2022 |
$500.00 |
-$450.00 |
$50.00 |
BOND |
1419 |
|
|
|
|
TOTAL |
$7,100.00 |
|
|
|