Pittsburgh Logo
File #: 2023-1663    Version: 1
Type: Resolution Status: Passed Finally
File created: 6/23/2023 In control: Committee on Public Works and Infrastructure
On agenda: 6/27/2023 Final action: 7/11/2023
Enactment date: 7/11/2023 Enactment #: 442
Effective date: 7/19/2023    
Title: Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a cost not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00). Future Resolutions will authorize the project specific service agreements.
Indexes: AGREEMENTS
Attachments: 1. 2023-1663 Cover Letter-Parking Lot Bridge RA Letter - signed, 2. Summary 2023-1663

title

Resolution providing for a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00). This resolution serves to authorize only the Reimbursement Agreement, at a cost not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00).  Future Resolutions will authorize the project specific service agreements.

 

body

Be it resolved by the Council of the City of Pittsburgh as follows:

 

Section 1.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project; providing for the payment of the costs thereof, not to exceed Six Hundred Twenty Five Thousand Dollars ($625,000.00) to be paid from the following accounts:

 

 

Phase

JDE JOB NO.

JDE FUND

BUDGET YEAR

AMOUNT

SOURCE

Preliminary Design

6031090223

40114

2023

$593,750.00

FHWA

 

6031090123

40023

2023

$31,250.00

BOND

 

 

 

TOTAL

$625,000.00

 

 

 

Section 2.                     The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement with the Commonwealth of Pennsylvania, Department of Transportation for the Preliminary Design phase of the Bridge over RT 51 Near Woodruff Street, also referred to as the Parking Lot Bridge Project providing for the payment of the costs thereof, not to exceed One Thousand Two Hundred and Fifty Dollars ($1,250.00), to be paid from the following account:

 

 

Phase

JDE JOB NO.

JDE FUND

BUDGET YEAR

AMOUNT

SOURCE

Preliminary Design

6031090123

40023

2023

$1,250.00

BOND

 

 

 

TOTAL

$1,250.00