File #:
|
2006-0360
Version:
1
|
|
|
Type:
|
Resolution
|
Status:
|
Passed Finally
|
On agenda:
|
|
Final action:
|
5/9/2006
|
Enactment date:
|
5/9/2006
|
Enactment #:
|
285
|
Effective date:
|
5/16/2006
|
|
|
Title:
|
Resolution Further amending Resolution No. 230, effective April 19, 2000, entitled "Providing for an Agreement or Agreements, or use of existing Agreements and/or a Contract or Contracts, or use of existing Contracts, and for the purchase of materials, supplies, equipment, and/or services for various projects in connection with the Neighborhood Needs Program in Council District 4; and providing for the payment of the costs thereof," by adding new line item "Colerain Retaining Wall" $12,821.00, and by decreasing "Overbrook Deck Hockey Court" by $3,636, "Banksville School Bathrooms" $8,000.00 and various other projects to reflect actual expenditures in Council District 4. Total of all projects is not to exceed $970,000.00
|
Indexes:
|
NEIGHBORHOOD NEEDS PROGRAM
|
Attachments:
|
1. 2006-0360.doc
|
Presenter
Presented by Mr. Shields
Title
Resolution Further amending Resolution No. 230, effective April 19, 2000, entitled "Providing for an Agreement or Agreements, or use of existing Agreements and/or a Contract or Contracts, or use of existing Contracts, and for the purchase of materials, supplies, equipment, and/or services for various projects in connection with the Neighborhood Needs Program in Council District 4; and providing for the payment of the costs thereof," by adding new line item "Colerain Retaining Wall" $12,821.00, and by decreasing "Overbrook Deck Hockey Court" by $3,636, "Banksville School Bathrooms" $8,000.00 and various other projects to reflect actual expenditures in Council District 4. Total of all projects is not to exceed $970,000.00
Body
Be it resolved that the Council of the City of Pittsburgh hereby enacts as follows:
Section 1. Section 1 of Resolution No. 230 effective April 19, 2000, as amended, which currently reads as per attachment Current Budget column;
Is hereby amended to read as per attachment Revised Budget column.
SEE ATTACHMENT
Attachment
Attachment |
|
|
|
Projects Account-Fund-Organization-Subclass-Project/Grant-Budget Year |
Current Budget |
Changes (+)(-) |
Revised Budget |
Able-Long Park Improvements |
$10,000.00 |
|
$10,000.00 |
Alton Field bathrms/Concession Stand Bldg. |
$40,000.00 |
|
$40,000.00 |
Alton Field Concession Stand Match |
$16,000.00 |
|
$16,000.00 |
Banksville School Field - Bathrooms |
$8,000.00 |
-$8,000.00 |
$ 0.00 |
600000-5100-101140-350-N105004-2000 |
|
|
|
Banksville School Field - plumbing work |
$5,454.54 |
|
$5,454.54 |
Banksville: traffic light/McMonagle & Meadwcrft |
$78,801.33 |
|
$78,801.33 |
Beechview Seldom Seen Greenway |
$2,709.01 |
|
$2,709.01 |
Beechview Trash Receptacles |
$4,992.00 |
|
$4,992.00 |
Beechview: St. Catherine's Senior Center |
$25,109.00 |
|
$25,109.00 |
Bon Air Playground |
$42,369.61 |
|
$42,369.61 |
Bon Air: memorial upgrades and landscaping |
$100,755.79 |
|
$100,755.79 |
Broadway Avenue Sidewalk Clean Up |
$3,000.00 |
|
$3,000.00 |
Brookline Library Project |
$29,229.96 |
|
$29,229.96 |
Brookline Park - concession bldg./20% match |
$16,000.00 |
|
$16,000.00 |
Brookline Memorial Park Scoreboard |
$9,500.00 |
-$1,000.00 |
$8,500.00 |
600000-5100-101140-350-N218011-2000 |
|
|
|
Brookline Park Renovations |
$9,272.72 |
|
$9,272.72 |
Brownsville Road Flags |
$3,600.00 |
|
$3,600.00 |
Brownsville Road pole removal |
$12,482.75 |
|
$12,482.75 |
Brownsville Road trash receptacles |
$6,145.70 |
|
$6,145.70 |
Carrick: Sinton Ave playground |
$60,000.00 |
|
$60,000.00 |
District 4 Field Improvements |
$14,000.00 |
|
$14,000.00 |
Fairhaven GW Taskforce Greenway Improvts. |
$96,756.00 |
|
$96,756.00 |
Fencing for Vanucci Field |
$73,704.64 |
|
$73,704.64 |
Greenway park development |
$3,244.00 |
|
$3,244.00 |
Hargrove Street Paving |
$7,420.90 |
|
$7,420.90 |
Install fence - Volunteers Field |
$2,432.00 |
|
$2,432.00 |
Lighting & restoration of Brookline Mural |
$10,367.95 |
|
$10,367.95 |
Little League dugouts |
$19,135.21 |
|
$19,135.21 |
Moore Park Replacement Equipment |
$5,792.04 |
|
$5,792.04 |
Mount Washington: Boggs Ave playground |
$80,000.00 |
|
$80,000.00 |
Overbrook:Deck Hockey Court |
$3,636.00 |
-$3,636.00 |
$ 0.00 |
600000-5100-101140-350-N105001-2000 |
|
|
|
Paint light poles |
$40,150.00 |
|
$40,150.00 |
Phillips Park walking path @ Sinton Ave |
$12,700.00 |
|
$12,700.00 |
Public Works Street Improvements |
$51,326.05 |
|
$51,326.05 |
Vanucci Field renovations |
$43,000.00 |
|
$43,000.00 |
Brookline Memorial Park Flagpole |
$2,400.00 |
-$185.00 |
$2,215.00 |
600000-5100-101140-350-N225021-2000 |
|
|
|
P.W.S.A. District 4 Projects |
$20,512.80 |
|
$20,512.80 |
Colerain Retaining Wall |
$ 0.00 |
+$12,821.00 |
+$12,821.00 |
600000-5100-101140-350- -2000 |
|
|
|
|
$953,481.59 |
$16,518.41 |
$970,000.00 |
|