Pittsburgh Logo
File #: 2007-1567    Version: 1
Type: Resolution Status: Passed Finally
File created: 6/26/2007 In control: Committee on Engineering, Fleet and Forestry
On agenda: Final action: 7/17/2007
Enactment date: 7/17/2007 Enactment #: 394
Effective date: 7/19/2007    
Title: Resolution repealing Resolution No. 558, effective November 30, 2004, entitled “Resolution providing for an Agreement or Agreements or for the use of existing Agreements with a Consultant or Consultants, for preliminary engineering in connection with the Wood Street Reconstruction, Phase II, including Project Management Services; providing for a Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania; and further providing for the payment of the costs thereof; at a cost not to exceed $500,000.00,” by repealing it in its entirety.
Indexes: AGREEMENT (REPEALING)
Attachments: 1. 2007-1567.doc
Presenter
Presented by Mrs. Harris
 
Title
Resolution repealing Resolution No. 558, effective November 30, 2004, entitled "Resolution providing for an Agreement or Agreements or for the use of existing Agreements with a Consultant or Consultants, for preliminary engineering in connection with the Wood Street Reconstruction, Phase II, including Project Management Services; providing for a Reimbursement Agreement or Agreements with the Commonwealth of Pennsylvania; and further providing for the payment of the costs thereof; at a cost not to exceed $500,000.00," by repealing it in its entirety.
 
Body
Be it resolved by the Council of the City of Pittsburgh as follows:
 
Section 1.      Section 1 of Resolution No. 558, effective November 30, 2004, which presently reads as follows:
 
"The Mayor and the Director of the Department of Engineering and Construction, on behalf of the City of Pittsburgh, are hereby authorized to enter into an Agreement or Agreements or to use existing Agreements, in form approved by the City Solicitor, with a Consultant or Consultants for engineering services related to the preliminary design in connection with the Wood Street Reconstruction, Phase II, including Project Management Services, at a cost not to exceed $500,000.00, chargeable to and payable from the following account:
 
Account      600000
Fund            5100
Org            301000
Sub-Class      PGHPR
Project/Grant      2231004
Budget Year      2004
Amount      $100,000
Source            CITY
 
Account      600000
Fund            5100
Org            301000
Sub-Class      PGHPR
Project/Grant      2231004
Budget Year      2004
Amount      $400,000
Source            FHWA
 
TOTAL      $500,000
 
 
 
Section 2.      The Mayor and the Director of the Department of Engineering and Construction, on behalf of the City of Pittsburgh, are hereby authorized to enter into a Reimbursement Agreement or Agreements, in form approved by the City Solicitor, with the Commonwealth of Pennsylvania, Department of Transportation, for the reimbursement to the City of Pittsburgh of the Federal Government's share of costs in connection with the reconstruction of Wood Street, Phase II,"
 
is hereby repealed in its entirety.